Aviation

Aviation Complex

Under Construction

Project Budget: $17,500,000

Designer:LS3P

CM at Risk: Not selected

Construction documents are complete and have been submitted to the State Construction Office for review.

School of Education

School of Education

Completed

Project Budget: $18,689,507

Designer: The Freelon Group

CM at Risk: DPR

This is a three story 48,000 square foot structure designed to house the School of Education and Psychology. Construction began August 2010 and is expected to be complete December 2011.

new dorm

New Dormitory

Completed August 2012

Project Budget: $13,500,000

Designer: Millennium Design Group

CM at Risk: Burney & Burney

This is a three story 64,000 square foot dormitory designed to house 228 students. Construction began May 2011 and is expected to be complete August 2012.

moorehall

Moore Hall Auditorium Restoration

Completed September 2011

Project Budget: $530,000

Designer: Clearscapes

GCProgressive Contracting

ECSU received an ARRA grant from the National Park Service to restore the Moore Hall auditorium. Construction began May 2011 and is expected to be complete September 2011.